Duration:
Oct 24 – Aug 25
Scope:
Duration:
Nov 23 – July 25
Scope:
CN196813PW
CN196814PW / CN196817PW
CN196815PW
CN196816PW
Duration:
Jun 23 – Mar 24
Scope:
Stormwater
Jacob Street Works (North of French Avenue)
Connection to Existing Culvert (Downstream)
Installation of DN450 & DN750 Pipework
Construction of 3 x Grated Gully Pits B1, B2, B3
Connection to Existing Upstream DN450 Pipe
French Avenue Works (South Side)
Connection to Existing Culvert (Downstream)
Installation of the 900×900 RC Box Culverts
Construction of Large Capacity Inlet Pit C1
Adjust Grate & Lintel to Pit D1
French Avenue Works (North Side)
Connection to Existing Culvert (Downstream)
Installation of the 900×900 RC Box Culverts
Installation of DN750, DN600 & DN300 RCP (Reinforced Concrete Pipes)
Construction of SAG Gully Pits A1, A2, A3
Connection to Existing Upstream DN600 & DN250 Pipes
Potable Water Main (French Avenue)
Installation of DN200 DICL (Ductile Iron Cement Lined) pipework underneath the stormwater asset.
Duration:
Sept 23 – Mar 24
Scope:
Wastewater:
Stormwater:
Civils / Power
Managing development approvals and compliance.
Duration:
Apr 24 – Nov 24
Scope:
Pipework
Duration:
July 24 – Dec 25
Scope:
PWG performed the scope of works for Fulton Hogan on behalf of TfNSW. This flagship project shows PWG’s expertise with water & sewer mains for tier one customers.
The scope of work included:
62m x DN100 DICL
110m x DN180 HDPE
16m x DN300 u.P.V.C (concrete encasement)
150m x DN225 u.P.V.C SN8
5 x manholes
